At a specific construction site, soil excavated from a borrow site and used as a fill. The borrow site water content is 26% and the solids specific gravity is 2.65. Standard Proctor Compaction tests resulted in a maximum dry unit weight of 105 pcf at optimum moisture content of 20%. Contract specifications require 95% relative compaction. However, at the site, the contractor complains that the fill pumps and ruts badly before reaching the required dry unit weight.

a. Draw the zero air voids curve for the fill soil (use spreadsheet, i. e. excel)
b. What is the maximum possible water content at 95% relative compaction?
c. If the soil is compacted at the natural water content of 26%, what is the maximum possible dry unit weight (without pumping)?
d. Briefly explain if the contractors’ argument is valid?

ansver
Answers: 1

Another question on Engineering

question
Engineering, 03.07.2019 15:10
Apiston-cylinder with a volume of 0.25 m3 holds 1 kg of air (r 0.287 k/kgk) at a temperature of 100 c. heat transfer to the cylinder causes an isothermal expansion of the piston until the volume triples. how much heat is added to the piston-cylinder?
Answers: 3
question
Engineering, 04.07.2019 18:20
Asolid cylinder is concentric with a straight pipe. the cylinder is 0.5 m long and has an outside diameter of 8 cm. the pipe has an inside diameter of 8.5 cm. the annulus between the cylinder ad the pipe contains stationary oil. the oil has a specific gravity of 0.92 and a kinematic viscosity of 5.57 x 10-4 m2/s. most nearly, what is the force needed to move the cylinder along the pipe at a constant velocity of 1 m/s?
Answers: 3
question
Engineering, 04.07.2019 19:20
Determine the time of the day and month of the year at which the peak sensible cooling load occurs for a top floor, north-eastern corner room of an office building in durban for the following conditions: floor area: 8 x 8 x 3 m east and north walls: 115 mm face brick (outside), 20 mm air space, 115 mm ordinary brick (inside) with 15 mm plaster roof construction: suspended plasterboard ceiling, 450 mm air space, 150 mm concrete, 75mm screed, waterproofing no heat transfer across other surfaces window area 3x 1,5 m high in north wall only. ordinary glass with venetian blinds. lights and occupants : from 07: 00 to 18: 00 average light density: 25 w/m2 number of occupants : 5 seated, light office work room temperature 24°c
Answers: 3
question
Engineering, 05.07.2019 04:30
Technician a says that in a worm gear steering system, most excessive steering free play is usually found in the gearbox. technician b says that in a rack-and-pinion steering system, excessive free play can be found in the bushings. who is correct?
Answers: 2
You know the right answer?
At a specific construction site, soil excavated from a borrow site and used as a fill. The borrow si...
Questions
question
English, 21.12.2019 04:31
question
Mathematics, 21.12.2019 04:31
Questions on the website: 13722363