A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

Please answer and thank you

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 21.06.2019 18:50
Using the artofstat website, run a permutation test to see if there is a difference in the mean amount of time spent on emails per day between in state and out of state students. (make sure to generate 10,000 permutations.) in state students: 2 3 3 6 2 1 1 5 3 2.5 out of state students: 1 2 2 1 2 1 4 3 9 1 10 1 3 what is the p-value?
Answers: 3
question
Computers and Technology, 22.06.2019 16:30
Technician a says that a dry sump system uses no oil storage sump under the engine. technician b says that a wet sump system uses no oil storage sump under the engine. who is correct?
Answers: 3
question
Computers and Technology, 22.06.2019 19:10
How might the success of your campaign be affected if you haven’t carefully completed all field data or if you accidentally insert the wrong merge field in the document?
Answers: 1
question
Computers and Technology, 23.06.2019 05:00
Which best explains why a digital leader would join a society specializing in technology
Answers: 1
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
Mathematics, 25.09.2019 05:10
question
Mathematics, 25.09.2019 05:10
question
Mathematics, 25.09.2019 05:10
Questions on the website: 13722367