A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

1. If activity E is delayed by 3 days how is the project completion time affected? Why is this the case?

2. If activity F is delayed by 3 days how is the project completion time affected? Why is this the case? Will the critical path change, why or why not?

3. If you want to shorten (crash) the overall time of this project, how do you pick which activity to shorten? What information, if any, do you need?

4. Once you shorten (crash) an activity, do you need to redo the AON, yes or no? Why or why not?

ansver
Answers: 2

Another question on Social Studies

question
Social Studies, 22.06.2019 14:30
What service name do you like? 1.schoolbrella 2.schoolplicity 3.studentaxle 4.studiley 5.edulliance 6.savantsnap 7.peaklemon 8.swiftgrasp 9.educaco 10.vistarise 11.iqpursuit 12.studentpivot 13.edgyadvice 14.studenterra
Answers: 1
question
Social Studies, 22.06.2019 21:00
What happens after a star goes supernova? just wondering! [tex]supernova [/tex] answer asap i really wanna know!
Answers: 1
question
Social Studies, 23.06.2019 11:10
In the introduction of becoming mexican american, sanchez draws from stuart hall's notion of cultural identity (pg. 12-13). hall asserts that identities are enmeshed in "becoming and of being." they are subjected to the elements and context of history. explain what you think he means by the idea of becoming and being and explain how context fits into comprehending the american concept of manifest destiny.
Answers: 1
question
Social Studies, 23.06.2019 11:30
How did china's location impact trade and its development?
Answers: 1
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
Questions on the website: 13722364