Technical constraints have been carefully considered when developing a project network. which of the following is true at this point? select one:
a. all of these are true statements once technical constraints have been established
b. resources have been assigned to each activity so they are adequate to complete the project on time
c. the project completion date can be established
d. the project is ready to be implemented
e. technical dependencies between activities are known
Answers: 1
Social Studies, 22.06.2019 10:20
Functionalism was a school of psychology that focused attention on the
Answers: 1
Social Studies, 22.06.2019 14:40
Which term describes a possible explanation of, or answer to, a scientific question that is based on prior knowledge or research and that is testable?
Answers: 2
Social Studies, 22.06.2019 20:00
What trade did europeans want most before the 1800s ivory wood slaves gold
Answers: 2
Technical constraints have been carefully considered when developing a project network. which of the...
Mathematics, 31.10.2020 01:00
Biology, 31.10.2020 01:00
Chemistry, 31.10.2020 01:00
History, 31.10.2020 01:00
Mathematics, 31.10.2020 01:00
Spanish, 31.10.2020 01:00
Health, 31.10.2020 01:00
English, 31.10.2020 01:00
History, 31.10.2020 01:00
Arts, 31.10.2020 01:00
Mathematics, 31.10.2020 01:00