If A, B, and C are three activities connected with SS and FF (combination) relationships with 2-day lag on SS relationship only. Their durations are 5, 10, and 3 respectively. What is the duration of the project?a. 5 days. b. 10 days. c. 3 days. d 18 days.

ansver
Answers: 3

Another question on Physics

question
Physics, 22.06.2019 16:30
Iron is a transition metal with multiple oxidation numbers. (answer the following) a. what is the iron (ii) ion? how does it differ from the iron (iii) ion? b. if iron were to bond with oxygen, predict the formula for each oxidation number of iron. c. how would each formula be named?
Answers: 2
question
Physics, 22.06.2019 19:00
The friction of the water on a boat produces an acceleration of -10. m/s2. if the boat is traveling at 30. m/s and the motor is shut off, how long it take the boat to slow down to 5.0 m/s?
Answers: 3
question
Physics, 22.06.2019 20:00
Positive ions differ from neutral atoms in that
Answers: 3
question
Physics, 23.06.2019 01:00
Which statement is true about an object that is moving in a circular motion due to centripetal force, f, when the radius of its circular motion is doubled? the new force then becomes equal to 2f the new force then becomes equal to f the new force then becomes equal to f/2 the new force then becomes equal to f2 the new force then becomes equal to 1/f
Answers: 1
You know the right answer?
If A, B, and C are three activities connected with SS and FF (combination) relationships with 2-day...
Questions
question
Mathematics, 16.11.2020 18:10
Questions on the website: 13722367