Physics, 03.07.2019 04:20 leslieperez67

Electric power is to be generated by installing a hydraulic turbine generator at a site 120 m below the free surface of a large water reservoir that can supply water at a rate of 2400 kg/s steadily. determine the power generation potential.

ansver
Answers: 1

Another question on Physics

question
Physics, 21.06.2019 20:30
Determine the amount of work done when a crane lifts a 100-n block form 2m above the ground to 6m above the ground
Answers: 1
question
Physics, 22.06.2019 07:30
The slope of a velocity time graph over any interval of time gives the during that interval
Answers: 1
question
Physics, 22.06.2019 10:30
Find the magnetic field a distance r from the center of a long wire that has radius a and carries a uniform current per unit area j in the positive z direction.
Answers: 2
question
Physics, 22.06.2019 11:30
With the simplified model of the eye, what corrective lens (specified by focal length as measured in air) would be needed to enable a person underwater to focus an infinitely distant object? (be careful-the focal length of a lens underwater is not the same as in air! assume that the corrective lens has a refractive index of 1.62 and that the lens is used in eyeglasses, not goggles, so there is water on both sides of the lens. assume that the eyeglasses are 1.90
Answers: 1
You know the right answer?
Electric power is to be generated by installing a hydraulic turbine generator at a site 120 m below...
Questions
question
Mathematics, 03.02.2020 09:54
question
Mathematics, 03.02.2020 09:54
question
English, 03.02.2020 09:54
Questions on the website: 13722361