3. Ting Group began work on a \7,000,000 contract in 2019 to construct an office building. During 2019, Ting Group incurred costs of \1,700,000, billed its customers for \1,200,000, and collected \960,000. At December 31, 2019, the estimated additional costs to complete the project total 3,300,000. Prepare Ting's 2019 journal entries using the percentage-of-completionmethod.

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 16:30
Adam plans to choose a video game from the section of the store where everything is 75% off. he writes the expression d-0.75d to find the sale price of the game if the original price is d dollars. gena correctly writes another expression, 0.25d, that will also find the sale price of the game if the original price is d dollars. use the drop down menus to explain each part of adams and rena's expression
Answers: 3
question
Mathematics, 21.06.2019 17:30
Thelime contains the point(-3,0) and parallel x-3y=3( show all work)
Answers: 3
question
Mathematics, 21.06.2019 23:50
Given δjkl : δxyz, find x. a)10 b)12 c)16 d)20
Answers: 2
question
Mathematics, 22.06.2019 00:00
Which of the following will form the composite function?
Answers: 3
You know the right answer?
3. Ting Group began work on a \7,000,000 contract in 2019 to construct an office building. During 20...
Questions
question
Mathematics, 26.02.2021 01:40
question
Mathematics, 26.02.2021 01:40
question
Mathematics, 26.02.2021 01:40
question
Chemistry, 26.02.2021 01:40
question
Mathematics, 26.02.2021 01:40
Questions on the website: 13722367