Mathematics, 10.12.2021 21:40 carealee

A contractor decides that he can build a house in eight weeks using 5 men. If he employs 3 more men, how long will the job take? Assume that all the men work at the same rate.

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 18:30
Which number line represents the solution set for the inequality -1/2x> 24?
Answers: 2
question
Mathematics, 21.06.2019 20:30
26) -2(7x) = (-2 • 7) x a. associative property of addition b. associative property of multiplication c. commutative property of multiplication d. commutative property of addition
Answers: 1
question
Mathematics, 21.06.2019 23:00
Calculate the average rate of change over the interval [1, 3] for the following function. f(x)=4(5)^x a. -260 b. 260 c. 240 d. -240
Answers: 1
question
Mathematics, 22.06.2019 00:30
How can you find the magnitude of a vector, v = < x,y > , where the horizontal change is x and the vertical change is y?
Answers: 1
You know the right answer?
A contractor decides that he can build a house in eight weeks using 5 men. If he employs 3 more men,...
Questions
question
Arts, 13.01.2021 04:10
question
Mathematics, 13.01.2021 04:10
question
Geography, 13.01.2021 04:10
question
Mathematics, 13.01.2021 04:10
question
Mathematics, 13.01.2021 04:10
Questions on the website: 13722363