you are planning to use PERT for planning of your project. A task has pessimistic estimate of 24 days, most likely estimate of 15 days and optimistic estimate of 12 days. what is the mean using the PERT technique

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 13:00
How can we find the measure of an exterior angle if we know the measurement of an interior angle
Answers: 2
question
Mathematics, 21.06.2019 16:00
Asap for seven months an ice creams vendor collects data showing the number of cones sold a day (c) and the degrees above 70 degrees f the vendor finds that there is a positive linear association between c and t that is the best modeled by this equation c=3.7t+98 which statement is true? the model predicts that the average number of cones sold in a day is 3.7 the model predicts that the average number of cones sold i a day is 98 a model predicts that for each additional degree that the high temperature is above 70 degres f the total of number of cones sold increases by 3.7 the model predicts for each additional degree that the high temperature is above 70 degrees f the total number of cones sold increasingly by 98
Answers: 3
question
Mathematics, 21.06.2019 17:30
If f(x)=3x+1 and f^-1=x-1/3, then f^-1(7)=
Answers: 1
question
Mathematics, 21.06.2019 20:00
Elizabeth is using a sample to study american alligators. she plots the lengths of their tails against their total lengths to find the relationship between the two attributes. which point is an outlier in this data set?
Answers: 1
You know the right answer?
you are planning to use PERT for planning of your project. A task has pessimistic estimate of 24 day...
Questions
question
Mathematics, 11.11.2020 16:40
question
Health, 11.11.2020 16:40
Questions on the website: 13722367