Mathematics, 18.09.2021 22:40 ThatStudent8769

Thomas can do a piece of work in 72 days; Clark can do it in 120 days; Smith can do it in 90 days. In what time can Smith, Thomas and Clark do it, working together?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 18:00
Describe the relationship between the angles of similar triangles and the sides of similar triangles
Answers: 1
question
Mathematics, 21.06.2019 19:00
The annual snowfall in a town has a mean of 38 inches and a standard deviation of 10 inches. last year there were 63 inches of snow. find the number of standard deviations from the mean that is, rounded to two decimal places. 0.44 standard deviations below the mean 2.50 standard deviations below the mean 0.44 standard deviations above the mean 2.50 standard deviations above the mean
Answers: 3
question
Mathematics, 21.06.2019 23:30
Graph the line with the given slope m and y-intercept b. m=-3,b=1
Answers: 1
question
Mathematics, 22.06.2019 02:00
90.0% complete a b c d e confirm last week, your delivery runs took 7 hours 12 minutes on monday, 6 hours 46 minutes on wednesday, and 6 hours 53 minutes on friday. what was your average time for a delivery run?
Answers: 3
You know the right answer?
Thomas can do a piece of work in 72 days; Clark can do it in 120 days; Smith can do it in 90 days. I...
Questions
Questions on the website: 13722363