Six men working 8 hours a day dig a shamba in 5 days. How many more days will it take 4 men working 8 hours a day to finish the job? NOTE:PLEASE EXPLAIN IN DETAIL !!!

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 20:00
Simplify 24÷(-2)(3)+7 a. -29 b. 3 c. 11
Answers: 1
question
Mathematics, 21.06.2019 20:40
In a 45-45-90 right triangle, what is the ratio of the length of one leg to the length of the other leg? а . 1: 2 в. 2: 1 с. 2: 1 d. 1: 1
Answers: 1
question
Mathematics, 21.06.2019 22:20
The coordinates of vortex a’ are (8,4) (-4,2) (4,-,4) the coordinates of vortex b’ are (6,6)(12,-,12)(12,12) the coordinates of vortex c’ are(-2,,12)(4,12)(12,-4)
Answers: 3
question
Mathematics, 21.06.2019 23:00
Janie has $3. she earns $1.20 for each chore she does and can do fractions of chores. she wants to earn enough money to buy a cd for $13.50.
Answers: 2
You know the right answer?
Six men working 8 hours a day dig a shamba in 5 days. How many more days will it take 4 men working...
Questions
question
Mathematics, 12.11.2019 16:31
question
Chemistry, 12.11.2019 16:31
Questions on the website: 13722363