Mathematics, 29.06.2021 09:40 chickennuggets0621

If 4 men can do a piece of work in 12 days, how many days will 6 men take.​

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 14:40
How many square feet of out door carpet will we need for this hole? 8ft 3ft 12ft 4ft
Answers: 1
question
Mathematics, 21.06.2019 19:00
Quadrilateral abcd in the figure below represents a scaled-down model of a walkway around a historic site. quadrilateral efgh represents the actual walkway. abcd is similar to efgh. what is the total length, in feet of the actual walkway?
Answers: 2
question
Mathematics, 21.06.2019 20:30
Pyramid shown has a square base that is 18 inches on each side has a surface area of 164 square inches what is the slant height
Answers: 3
question
Mathematics, 21.06.2019 21:00
Select the correct answer from each drop-down menu. a system of equations and its solution are given below. system a complete the sentences to explain what steps were followed to obtain the system of equations below. system b to get system b, the equation in system a was replaced by the sum of that equation and times the equation. the solution to system b the same as the solution to system a.]
Answers: 1
You know the right answer?
If 4 men can do a piece of work in 12 days, how many days will 6 men take.​...
Questions
question
Mathematics, 20.04.2020 21:15
question
Mathematics, 20.04.2020 21:16
Questions on the website: 13722367