subject
Mathematics, 27.05.2021 14:00 kaylyns134

)If there are 6 builders, it takes 80 days to complete the house. How many builders must be employed to build the house in just 16 days?โ€‹

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 14:30
Atriangular bandana has an area of 46 square inches. the height of the triangle is 5 3 4 inches. enter and solve an equation to find the length of the base of the triangle. use b to represent the length of the base.
Answers: 2
question
Mathematics, 21.06.2019 18:30
The clayton familyโ€™s pool has vertices at the coordinates (0, 2), (0, 5), (2, 5), (2, 6), (5, 6), (5, 1), (2, 1), and (2, 2). if each grid square has an area of 9 square feet, what is the area of the pool?
Answers: 1
question
Mathematics, 21.06.2019 20:40
The roots of the function f(x) = x2 โ€“ 2x โ€“ 3 are shown. what is the missing number?
Answers: 2
question
Mathematics, 21.06.2019 21:30
Find the missing dimension extra points
Answers: 2
You know the right answer?
)If there are 6 builders, it takes 80 days to complete the house. How many builders must be employed...
Questions
question
Mathematics, 25.05.2021 01:10
question
Mathematics, 25.05.2021 01:10
question
Mathematics, 25.05.2021 01:10
question
Mathematics, 25.05.2021 01:10
question
Mathematics, 25.05.2021 01:10
question
Mathematics, 25.05.2021 01:10
Questions on the website: 13722366