. A contractor determined the average amount of time needed to build a house. .
When 5 workers are used, it takes 52 days to build the house.
When 20 workers are used, it takes 13 days to build the house.
If w represents the number of workers and d represent the number of days required
to build the house, which statement is true about this relationship?
F.

The time required to build a house varies directly with the number of workers because
d = 260w.
The time required to build a house varies directly with the number of workers because
wd = 260.
The time required to build a house varies inversely with the number of workers because
d = 260w.
The time required to build a house varies inversely with the number of workers because
wd =260


. A contractor determined the average amount of time needed to build a house.

.
When 5 workers ar

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 19:10
What are the coordinates of the point that is 1/3 of the way from a to b? a (2,-3) b (2,6)
Answers: 3
question
Mathematics, 21.06.2019 19:40
Which of the following could be the ratio of the length of the longer leg 30-60-90 triangle to the length of its hypotenuse? check all that apply. a. 313 6 b. 3: 215 c. 18: 13 d. 1: 13 e. 13: 2 of. 3: 15
Answers: 3
question
Mathematics, 21.06.2019 20:00
Last one and the bottom answer choice is y=(x-4)^2+1 you guys!
Answers: 1
question
Mathematics, 21.06.2019 20:30
Which expression is equivalent to (4 +6i)^2? ? -20 + 48i 8 + 12i 16 - 36i 20 + 48i
Answers: 1
You know the right answer?
. A contractor determined the average amount of time needed to build a house. .
When 5 worker...
Questions
question
Chemistry, 26.07.2019 06:00
Questions on the website: 13722363