Your manufacturing requires parts to go sequentially through process A, B, and C. A machine can do process A in 1 minute, B in 2 minutes, and C in 3 minutes. You have two A machines, one B machine, and three C machines. Which process is the
bottleneck (can produce the fewest items per unit time)?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 16:30
Data are collected to see how many ice-cream cones are sold at a ballpark in a week. day 1 is sunday and day 7 is the following saturday. use the data from the table to create a scatter plot.
Answers: 3
question
Mathematics, 21.06.2019 16:50
Line l passes through points (0,4) and (3,6) what is the slope of a line that is parallel to line l -2/3 -3/2 2/3 3/2
Answers: 1
question
Mathematics, 21.06.2019 17:30
Danielle earns a 7.25% commission on everything she sells at the electronics store where she works. she also earns a base salary of $750 per week. what were her sales last week if her total earnings for the week were $1,076.25?
Answers: 3
question
Mathematics, 21.06.2019 20:00
Worth 30 points! in this diagram, both polygons are regular. what is the value, in degrees, of the sum of the measures of angles abc and abd?
Answers: 2
You know the right answer?
Your manufacturing requires parts to go sequentially through process A, B, and C. A machine can do p...
Questions
question
Chemistry, 25.01.2022 02:50
question
Mathematics, 25.01.2022 02:50
question
Social Studies, 25.01.2022 02:50
question
English, 25.01.2022 02:50
question
Mathematics, 25.01.2022 02:50
question
Geography, 25.01.2022 02:50
question
Mathematics, 25.01.2022 02:50
question
Physics, 25.01.2022 02:50
Questions on the website: 13722363