A new housing development will have 105 houses. All the houses have the same floor plan and dimensions. Carlos can paint a house by himself in 4 days. Manuel can paint a house in 3 days.
A normal workweek is 5 days how many weeks would it take them to work together to paint 105 houses?
now suppose that they need to finish in 28 weeks but only have enough to pay for one extra crew member. What is the greatest number of days the third
worker can take to paint each house?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 16:10
The probability that a college student belongs to a health club is 0.3. the probability that a college student lives off-campus is 0.4. the probability that a college student belongs to a health club and lives off-campus is 0.12. find the probability that a college student belongs to a health club or lives off-campus. tip: p(a or b) = p(a) + p(b) - p(a and b) 0.54 0.58 0.70 0.82
Answers: 2
question
Mathematics, 21.06.2019 17:00
Find the value of the variable and the length of each secant segment.
Answers: 1
question
Mathematics, 21.06.2019 19:30
At 6 1/2 cents per pound of string beans how much does 7 pounds cost
Answers: 1
question
Mathematics, 21.06.2019 23:00
Aremote-controlled boat can travel at 4 feet per second in calm water. the boat traveled 48 feet with the current, and then it traveled 16 feet against the current in the same amount of time. how fast is the current?
Answers: 1
You know the right answer?
A new housing development will have 105 houses. All the houses have the same floor plan and dimensio...
Questions
question
Biology, 31.07.2019 03:30
question
Mathematics, 31.07.2019 03:30
question
Mathematics, 31.07.2019 03:30
Questions on the website: 13722367