Construction company has four big front-end loaders located at four different workshops. The loaders must be moved to four different construction sites. The distances in kilometers are

tabulated below.

Loader A B C D Total distance

1 90 75 75 80 320

2 35 85 55 65 240

3 125 95 90 105 415

4 45 110 95 115 365

Total distance 295 365 315 365

Site

(a) How should the loaders be moved in order to minimize the total distance travelled? [6]

(b) Formulate the linear programming model for the data provided. [6]

(c) Formulate the dual model for the primal in (b). [6]

(d) Use the North-West Corner method to solve the problem. ​

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 15:00
There were 816 people at a concert when a band started to play. after each song, only half the people stayed to hear the next song. how many people were left at the concert after x songs? write a function to represent this scenario.
Answers: 3
question
Mathematics, 21.06.2019 20:00
With finding limits of multi variable !
Answers: 1
question
Mathematics, 21.06.2019 21:30
About 9% of th population is hopelessly romantic. if 2 people are randomly selected from the population, what is the probability that at least 1 person is hopelessly romantic?
Answers: 1
question
Mathematics, 22.06.2019 00:50
How does the graph of y = 3x compare to the graph of y = 3-x?
Answers: 1
You know the right answer?
Construction company has four big front-end loaders located at four different workshops. The loade...
Questions
question
English, 25.11.2021 05:30
question
Mathematics, 25.11.2021 05:30
Questions on the website: 13722366