A contractor employs 40 men to do a piece of work in 60 days. Each man working 9 hours per day. He then requested to do the job in 48 days. How many more men working 10 hours a day does he need to employ?​

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 19:00
How can you tell when x and y are not directly proportional?
Answers: 1
question
Mathematics, 21.06.2019 19:30
Vinay constructed this spinner based on the population of teachers at his school according to vinays model what is the probability that he will have a male history teacher two years in a row
Answers: 3
question
Mathematics, 21.06.2019 21:10
Hey free points ! people i have a few math questions on my profile consider looking at them i have to get done in 30 mins!
Answers: 1
question
Mathematics, 21.06.2019 23:30
How do you write 600 as a product of its prime factors (index! )
Answers: 1
You know the right answer?
A contractor employs 40 men to do a piece of work in 60 days. Each man working 9 hours per day. He t...
Questions
question
English, 21.02.2022 19:30
question
Mathematics, 21.02.2022 19:30
question
English, 21.02.2022 19:40
question
Mathematics, 21.02.2022 19:40
question
Mathematics, 21.02.2022 19:40
question
Physics, 21.02.2022 19:40
question
Mathematics, 21.02.2022 19:40
Questions on the website: 13722363