Processing times and due dates of 9 jobs are given as follows: Job 1 2 3 4 5 6 7 8 9
Proc Time 4 3 7 9 8 15 6 7 10
Due Date 35 40 44 25 20 43 40 22 38
Assume that all jobs arrive at time 0
a) Generate a schedule that minimizes the mean flow time. Break ties with the smallest job number first (i. e., if 3 and 8 have identical parameters, 3 should be scheduled first).
b) Calculate mean flow time, mean tardiness, and maximum tardiness of the schedule obtained in a)
c) Generate a schedule that minimizes the maximum tardiness. Break ties with the smallest job number first.
d) Calculate mean flow time, mean tardiness, and maximum tardiness of the schedule obtained in c)

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 18:30
Which of the following is the result of expanding
Answers: 2
question
Mathematics, 21.06.2019 20:30
3.17 scores on stats final. below are final exam scores of 20 introductory statistics students. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 57, 66, 69, 71, 72, 73, 74, 77, 78, 78, 79, 79, 81, 81, 82, 83, 83, 88, 89, 94 (a) the mean score is 77.7 points. with a standard deviation of 8.44 points. use this information to determine if the scores approximately follow the 68-95-99.7% rule. (b) do these data appear to follow a normal distribution? explain your reasoning using the graphs provided below.
Answers: 1
question
Mathematics, 21.06.2019 23:00
Someone answer this asap for the first five terms of a sequence are shown. 5, 11, 23, 47, 95, . . which recursive function defines the nth term in the sequence for n > 1? a. f(n) = f(n - 1) + 6 b) f(n) = f(n - 1) + 48 c) f(n) = 3 • f(n - 1) + 1 d) f(n) = 3 • f(n - 1) - 4
Answers: 1
question
Mathematics, 21.06.2019 23:20
In the diagram, be and ad pass throughthe center of circle o, and the area ofsector aoc is 47.45 square units. what isthe area of sector boc? use the value =3.14, and round your answer to two decimalplaces.22.33 square units25.12 square units
Answers: 2
You know the right answer?
Processing times and due dates of 9 jobs are given as follows: Job 1 2 3 4 5 6 7 8 9
Proc Ti...
Questions
question
Mathematics, 20.05.2021 06:00
question
Mathematics, 20.05.2021 06:00
Questions on the website: 13722363