28 men can finish the job in 60 days. at the start of the 16 day, 5 men were laid off and after the 45th, 10 more men were hired. how many days were delayed in finishing the job? explain, step by step.

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 14:30
Mr switzer needs to buy new 1-foot tiles to cover his bathroom floor. the floor is 12 feet long and 8 feet wide. each square foot of tile will cost $1.79. in dollars what will be the total cost of the tiles he needs to buy.
Answers: 3
question
Mathematics, 21.06.2019 17:40
Aperpendicular bisector, cd is drawn through point con ab if the coordinates of point a are (-3, 2) and the coordinates of point b are (7,6), the x-intercept of cd is point lies on cd.
Answers: 2
question
Mathematics, 21.06.2019 18:30
The measure of one angle of an octagon is two times smaller that of the other seven angles. what is the measure of each angle?
Answers: 3
question
Mathematics, 21.06.2019 19:00
Pyotr tchaikovsky sporting goods operates on a 45% overhead based on the selling price, which results in an overhead of $65.34 on the newest version of an air hockey game set. if the air hockey game set costs pyotr tchaikovsky sports $49.32, find the selling price, the markup, and the net profit.
Answers: 2
You know the right answer?
28 men can finish the job in 60 days. at the start of the 16 day, 5 men were laid off and after the...
Questions
question
Computers and Technology, 30.08.2019 21:30
question
Mathematics, 30.08.2019 21:30
question
English, 30.08.2019 21:30
question
Mathematics, 30.08.2019 21:30
question
Social Studies, 30.08.2019 21:30
Questions on the website: 13722363