7. When building a house, the number of days required to build is inversely proportional to
with the number of workers. Pne house was built in 11 days by 27 workers. How many
days would it take to build a similar house with 3 workers?
Answers: 2
Mathematics, 21.06.2019 14:30
Which system of linear inequalities is represented by the graph?
Answers: 2
Mathematics, 21.06.2019 20:30
Which shows the graph of the solution set of 3y – 2x > –18?
Answers: 1
Mathematics, 22.06.2019 00:30
Jan accidently ran 7 minutes longer than he was supposed to. write an expression for the total amount of time jan ran if she was supposed to run m minutes
Answers: 1
Mathematics, 22.06.2019 01:00
Find the rate of change for the situation.you run 7 miles in one hour and 21 miles in three hours.
Answers: 1
7. When building a house, the number of days required to build is inversely proportional to
with th...
Mathematics, 03.09.2021 01:00
Biology, 03.09.2021 01:00
Chemistry, 03.09.2021 01:00
Mathematics, 03.09.2021 01:00
Mathematics, 03.09.2021 01:00
Computers and Technology, 03.09.2021 01:00
Mathematics, 03.09.2021 01:00
Mathematics, 03.09.2021 01:00
Mathematics, 03.09.2021 01:00
Mathematics, 03.09.2021 01:00