10 workers can finish the job in 15days. For the first 5 days, only 6 workers worked on the job. Then for the next 3 days 2 more workers joined them. To finish the job, 4 more workers joined them. After how many days was the whole job done?
Answers: 1
Mathematics, 21.06.2019 13:00
In the diagram below, dab and dac are adjacent angles. if mdac = 25°, what is mdab in degrees? what is mbac in degrees?
Answers: 3
Mathematics, 21.06.2019 18:00
The los angels ram scored 26, 30, 48, and 31 pts in their last four games. how many pts do they need to score in super bowl liii in order to have an exact mean average of 35 pts over five games. write and solve and equation. use x to represent the 5th game.
Answers: 1
Mathematics, 21.06.2019 18:00
Janie has $3. she earns $1.20 for each chore she does and can do fractions of chores. she wants to earn enough money to buy a cd for $13.50. write an inequality to determine the number of chores, c, janie could do to have enough money to buy the cd.
Answers: 1
Mathematics, 21.06.2019 19:30
Vinay constructed this spinner based on the population of teachers at his school according to vinays model what is the probability that he will have a male history teacher two years in a row
Answers: 3
10 workers can finish the job in 15days. For the first 5 days, only 6 workers worked on the job. The...
Advanced Placement (AP), 07.12.2020 03:00
Mathematics, 07.12.2020 03:00
Mathematics, 07.12.2020 03:00
Mathematics, 07.12.2020 03:00
Mathematics, 07.12.2020 03:00
Law, 07.12.2020 03:00
Mathematics, 07.12.2020 03:00
Engineering, 07.12.2020 03:00
English, 07.12.2020 03:00
Physics, 07.12.2020 03:00
Mathematics, 07.12.2020 03:00