DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month
1 2 3 4
Throughput time (days) ? ? ? ?
Delivery cycle time (days) ? ? ? ?
Manufacturing cycle efficiency (MCE) ? ? ? ?
Percentage of on-time deliveries 78 % 73 % 70 % 67 %
Total sales (units) 2330 2230 2116 2036
Management has asked for your help in computing throughput time, delivery cycle time, and MCE. The following average times have been logged over the last four months:
Average per Month (in days)
1 2 3 4
Move time per unit 0.8 0.4 0.5 0.5
Process time per unit 3.4 3.2 3.0 2.8
Wait time per order before start of production 23.0 25.2 30.0 32.3
Queue time per unit 4.3 5.1 6.0 7.0
Inspection time per unit 0.6 0.9 0.9 0.6
Required:
1-a. Compute the throughput time for each month.
1-b. Compute the delivery cycle time for each month.
1-c. Compute the manufacturing cycle efficiency (MCE) for each month.
2. Evaluate the company’s performance over the last four months.
3-a. Refer to the move time, process time, and so forth, given for month 4. Assume that in month 5 the move time, process time, and so forth, are the same as in month 4, except that through the use of Lean Production the company is able to completely eliminate the queue time during production. Compute the new throughput time and MCE.
3-b. Refer to the move time, process time, and so forth, given for month 4. Assume in month 6 that the move time, process time, and so forth, are again the same as in month 4, except that the company is able to completely eliminate both the queue time during production and the inspection time. Compute the new throughput time and MCE.

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 13:00
What is the maximum total area that 450cm of string can enclose if it is used to form perimeters of two adjoining rectangles as shown?
Answers: 1
question
Mathematics, 21.06.2019 19:50
Drag each tile into the correct box. not all tiles will be used. find the tables with unit rates greater than the unit rate in the graph. then tenge these tables in order from least to greatest unit rate
Answers: 2
question
Mathematics, 21.06.2019 23:00
Solve for n. round to the tenths place, if necessary. 14.2 cups of flour6 loaves of bread= 20 cups of flour n
Answers: 2
question
Mathematics, 21.06.2019 23:30
Find the measure of angle y. round your answer to the nearest hundredth. ( type the numerical answer only) a right triangle is shown with one leg measuring 5 and another leg measuring 14. an angle across from the leg measuring 5 is marked y degrees. numerical answers expected!
Answers: 1
You know the right answer?
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufa...
Questions
question
Mathematics, 20.09.2020 07:01
question
Mathematics, 20.09.2020 07:01
question
Mathematics, 20.09.2020 07:01
question
Mathematics, 20.09.2020 07:01
Questions on the website: 13722363