if 9 men can complete a job in 4 days, how long will 8 men take to complete the same job, assuming that all the men are working at the same rate?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 12:30
Use the function nest to evaluate p(x) = 1 + x + · · · + x50 at x = 1.00001. (use the matlab ones command to save typing.) find the error of the computation by comparing with the equivalent expression q(x) = (x51 − 1)/(x − 1).
Answers: 3
question
Mathematics, 21.06.2019 15:00
This is the number of parts out of 100, the numerator of a fraction where the denominator is 100. submit
Answers: 3
question
Mathematics, 21.06.2019 15:30
Asquare is dilated by a scale factor of 1.25 to create a new square. how does the area of the new square compare with the area of the original square? a)the area of the new square is 1.25 times the area of the original square. b)the area of the new square is 2.50 times the area of the original square. c)the area of the new square is 1.252 times the area of the original square. d)the area of the new square is 1.253 times the area of the original square.
Answers: 1
question
Mathematics, 21.06.2019 16:30
A(t)=728(1+0.04)^t how much money did aditya originally invest
Answers: 1
You know the right answer?
if 9 men can complete a job in 4 days, how long will 8 men take to complete the same job, assuming t...
Questions
question
Mathematics, 08.07.2019 01:00
question
Mathematics, 08.07.2019 01:00
question
Mathematics, 08.07.2019 01:00
Questions on the website: 13722367