Mary, John and Sue are working on a large project. From past experience it is estimated that Mary would require 45 days to complete the project, John would require 50 days, and Sue would require 60 days. If they work together, what would be the estimated number of days required to complete this project? I v

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 14:50
Need to increase the numbers of customers i talk to daily by 20% how many customers do i need to talk to if i talk to a average of 8 customers per hour during an 8 hour shift
Answers: 2
question
Mathematics, 21.06.2019 17:30
Student price tickets to a movie are $1 and non student tickets are $2 . 350 tickets are sold and the total amount made is $450. there were 250 student tickets sold . true or false .
Answers: 1
question
Mathematics, 21.06.2019 18:00
Solve this system of equations. 12x − 18y = 27 4x − 6y = 10
Answers: 1
question
Mathematics, 21.06.2019 18:30
What is the prime factorization of 230
Answers: 1
You know the right answer?
Mary, John and Sue are working on a large project. From past experience it is estimated that Mary wo...
Questions
question
Mathematics, 07.07.2021 18:00
question
Mathematics, 07.07.2021 18:00
question
Chemistry, 07.07.2021 18:00
question
History, 07.07.2021 18:00
question
Physics, 07.07.2021 18:00
question
Mathematics, 07.07.2021 18:00
Questions on the website: 13722363