It will take 48 hours of work to complete the garden. The garden must be finished in 3 days.
Each gardener works for 8 hours per day.
How many gardeners are needed?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 15:00
The head librarian at the library of congress has asked her assistant for an interval estimate of the mean number of books checked out each day. the assistant provides the following interval estimate: from 740 to 920 books per day. what is an efficient, unbiased point estimate of the number of books checked out each day at the library of congress?
Answers: 3
question
Mathematics, 21.06.2019 15:30
Will mark brainliest if you answer ! the taco shop sold 198 lunches friday. this number is 3 more than 3 times the number they sold monday. let n represent the number of lunches sold monday. which equation shows an equality between two different ways of expressing the number of lunches sold on friday? a. n – 3 = 198 b. 3n – 3 = 198 c. 3n + 3 = 198 d. n + 3 = 198
Answers: 1
question
Mathematics, 21.06.2019 17:00
Measures of the angle of r, 31 s (x+4) t (3x+9)
Answers: 1
question
Mathematics, 21.06.2019 18:00
Arecipe calls for 2 2/4 cups of raisins, but julie only has a 1/4 measuring cup. how many 1/4 cups is needed to measure out 2 2/4 cups of raisins?
Answers: 1
You know the right answer?
It will take 48 hours of work to complete the garden. The garden must be finished in 3 days.
...
Questions
question
Physics, 30.10.2020 20:50
question
Mathematics, 30.10.2020 20:50
question
Mathematics, 30.10.2020 20:50
Questions on the website: 13722367