The number of days, d, to build a house is given by 780
d =
W
where w is the number of workers used each day on site.
Bob's company will take 60 days to build the house.
Pat's company will take 39 days to build the house.
Pat's company will have to use more workers each day than Bob's company.
How many more?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 19:30
Aline passes through 3,7 and 6,9 what equation represents the line
Answers: 2
question
Mathematics, 21.06.2019 20:30
Create a question with this scenario you could ask that could be answered only by graphing or using logarithm. david estimated he had about 20 fish in his pond. a year later, there were about 1.5 times as many fish. the year after that, the number of fish increased by a factor of 1.5 again. the number of fish is modeled by f(x)=20(1.5)^x.
Answers: 1
question
Mathematics, 21.06.2019 21:30
Joe has a rectangular chicken coop. the length of the coop is 4 feet less than twice the width. the area of the chicken coop is 510 square feet. what is the length of the chicken coup?
Answers: 3
question
Mathematics, 21.06.2019 23:00
10x − 5y + 14 = 0 whats the answer pls
Answers: 2
You know the right answer?
The number of days, d, to build a house is given by 780
d =
W
where w is the numb...
Questions
question
Mathematics, 21.08.2019 22:50
question
Mathematics, 21.08.2019 22:50
question
Mathematics, 21.08.2019 22:50
Questions on the website: 13722363