2. A road 750 metres long is to be resurfaced.
(a)
Workalot say they can resurface it in 23 days.
How many metres is this each day?
Give your answer to the nearest metre.
(b) Roadfill say they can resurface 40 metres of the road each day.
How many days will it take them to do the job?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 18:40
This stem-and-leaf plot represents the heights of the students on ralph's basketball team. one student's height is missing from the plot. if the mean height of all the students on the team is 61 inches, what is the missing height? a. 55 in. b. 59 in. c. 61 in. d. 65 in.
Answers: 2
question
Mathematics, 21.06.2019 21:30
Noel is hoping to make a profit (in $) on the school play and has determined the function describing the profit to be f(t) = 8t – 2654, where t is the number of tickets sold. what does the number 8 tell you?
Answers: 1
question
Mathematics, 21.06.2019 23:30
The perimeter of an equilateral triangle is 4 cm more than the perimeter of a square and the length of a side of the triangle is 8 cm more than the length of a side of the aware. find the length of a side of the equilateral triangle
Answers: 1
question
Mathematics, 21.06.2019 23:30
Dots sells a total of 279 t-shirts ($2) and shorts ($4). in april total sales were $670. how many t-shirts and shorts did dots sell?
Answers: 1
You know the right answer?
2. A road 750 metres long is to be resurfaced.
(a)
Workalot say they can resurface it i...
Questions
question
History, 01.08.2019 01:00
Questions on the website: 13722362