The time (t) required to finish a certain job is inversely proportional to the number of persons (p) on the job. If 10
persons can finish the job in 6 hours, how long will it take
for 30 persons to finish the job?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 13:00
He expression 2(l + w) is used to calculate the perimeter of a rectangle, where l is length and w is width. if the length is fraction 2 over 3 unit and the width is fraction 1 over 3 unit, what is the perimeter of the rectangle in units? fraction 2 over 3 unit 1 unit 1fraction 2 over 3 units 2 units
Answers: 3
question
Mathematics, 21.06.2019 17:30
11. a particular type of cell doubles in number every hour. which function can be used to find the number of cells present at the end of h hours if there are initially 4 of these cells? a. n = 4 ()" b. n = 4(2)" c. n = 4 + (2)" din = 4 +"
Answers: 1
question
Mathematics, 21.06.2019 19:00
Astore has apples on sale for three dollars or 2 pounds how many pounds of apples can you buy for nine dollars if an apple is approximately 5 ounces how many apples can you buy for nine dollars
Answers: 1
question
Mathematics, 21.06.2019 19:30
Evaluate the expression for the given value of the variable. ∣-4b-8∣+∣-1-b^2 ∣+2b^3 ; b=-2
Answers: 2
You know the right answer?
The time (t) required to finish a certain job is inversely proportional to the number of persons (p...
Questions
question
World Languages, 18.03.2021 01:20
question
English, 18.03.2021 01:20
question
Mathematics, 18.03.2021 01:20
question
Social Studies, 18.03.2021 01:20
question
Mathematics, 18.03.2021 01:20
question
Geography, 18.03.2021 01:20
Questions on the website: 13722367