a group of 4 pupils can take 2 weeks to do a certain job. how long will 12 pupils take to complete the job if they work at the same rate

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 16:30
In the figure shown below, m < 40 and ab =8. which equation could be used to find x?
Answers: 2
question
Mathematics, 21.06.2019 17:40
Find the x-intercepts of the parabola withvertex (1,1) and y-intercept (0,-3).write your answer in this form: (x1,if necessary, round to the nearest hundredth.
Answers: 1
question
Mathematics, 21.06.2019 22:20
Which of the following is missing in the explicit formula for the compound interest geometric sequence below?
Answers: 1
question
Mathematics, 21.06.2019 23:00
Rob filled 5 fewer plastic boxes with football cards than basketball cards. he filled 11 boxes with basketball cards.
Answers: 1
You know the right answer?
a group of 4 pupils can take 2 weeks to do a certain job. how long will 12 pupils take to complete t...
Questions
question
Health, 12.02.2020 22:05
question
Physics, 12.02.2020 22:05
Questions on the website: 13722363