Mathematics, 03.01.2021 22:10 madelyngv97

A group of 9 workers was assigned to paint the walls in a house, which could be completed in 48 hours. However, after working 8 hours, some of the workers left the group and the remaining workers could complete the job in 72 hours. How many workers left the team? Plz write equation:0

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 21:30
Complete each statement from the information given and the triangle criterion you used. if the triangles cannot be shown to be congruent, leave the box for the second triangle blank and choose for reason “cannot be determined.” carbon - regular hexagon. ∆can ≅ ∆ by
Answers: 1
question
Mathematics, 21.06.2019 22:30
Will mark determine whether the conjecture is true or false. give a counterexample for any false conjecture. given: points r, s, and t conjecture: r, s, and t are coplanar. a) false; the points do not have to be in a straight line. b) true c) false; the points to not have to form right angles. d) false; one point may not be between the other two.
Answers: 1
question
Mathematics, 22.06.2019 01:00
The ideal weight of a nickel is 0.176 ounce. to check that there are 40 nickels in a roll, a bank weighs the roll and allows for an error of 0.015 ounce in total weight
Answers: 1
question
Mathematics, 22.06.2019 01:00
Ataxi company charges $3 for pick-up plus $0.65 for each mile. select the expressions that represent the cost in dollars for a taxi pick-up and m miles. mark all that apply.
Answers: 1
You know the right answer?
A group of 9 workers was assigned to paint the walls in a house, which could be completed in 48 hour...