if 3 people can complete a job in 4 days, how many days will it take to complete the job with 5 people?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 15:00
7(x - 2) = 3(x + 4) solve the following equation. then enter your answer in the space provided using mixed number format.
Answers: 2
question
Mathematics, 21.06.2019 15:30
Iwill give brainliest only if your correct the words subsequent and submerge both contain the prefix sub. based on this information, what does the prefix sub most likely mean? a) under or secondary b) true or verifiable c) tricky or difficult d) around or centered on
Answers: 1
question
Mathematics, 21.06.2019 20:30
Aswimming pool had 2.5 million liters of water in it. some water evaporated, and then the pool only had 22 million liters of water in it. what percent of the water evaporated?
Answers: 2
question
Mathematics, 21.06.2019 20:50
What is the greatest number of parts of a circle that can be formed by cutting the circle with 7 straight cuts? (note: the parts do not have to be equal in size)
Answers: 3
You know the right answer?
if 3 people can complete a job in 4 days, how many days will it take to complete the job with 5 peop...
Questions
question
Mathematics, 04.07.2019 12:30
question
Chemistry, 04.07.2019 12:30
question
Mathematics, 04.07.2019 12:30
question
Biology, 04.07.2019 12:30
question
Biology, 04.07.2019 12:30
Questions on the website: 13722361