Mathematics, 20.11.2020 17:50 triddi666

A contractor must haul a large amount of dirt to a work site. She collected information from two hauling companies. EZ Excavation gives its prices in a table. Happy Hauling Service gives its prices in a graph. dirt (cubic yards)cost (dollars)
row 18196
row 220490
row 326637

How much would each hauling company charge to haul 40 cubic yards of dirt? Explain or show your reasoning.

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 21:30
Amachine part consists of a half sphere and a cylinder, as shown in the figure. the total volume of the part is π cubic inches.
Answers: 1
question
Mathematics, 21.06.2019 22:00
Write a description of each inequality. 1. -5a + 3 > 1 2. 27 - 2b < -6 (this < has a _ under it) 3. 1/2 (c + 1) > 5 (this > has a _ under it)
Answers: 3
question
Mathematics, 21.06.2019 23:00
Find the rate at which the water is now flowing from the tap give your answer cubic centimetres per second
Answers: 1
question
Mathematics, 22.06.2019 00:30
Describe how to translate the graph of y=/x to obtain the graph of y=/x+5
Answers: 2
You know the right answer?
A contractor must haul a large amount of dirt to a work site. She collected information from two hau...
Questions
question
Mathematics, 02.06.2020 22:58
Questions on the website: 13722361