subject
Mathematics, 12.11.2020 23:40 miraculousdollh

In a survey of 2,700 people who owned a certain type of car, 1,485 said they would buy that type of car again. What percent of the people surveyed were satisfied with the car

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 18:00
Someone answer this asap rn for ! a discount store’s prices are 25% lower than department store prices. the function c(x) = 0.75x can be used to determine the cost c, in dollars, of an item, where x is the department store price, in dollars. if the item has not sold in one month, the discount store takes an additional 20% off the discounted price and an additional $5 off the total purchase. the function d(y) = 0.80y - 5 can be used to find d, the cost, in dollars, of an item that has not been sold for a month, where y is the discount store price, in dollars. create a function d(c(x)) that represents the final price of an item when a costumer buys an item that has been in the discount store for a month. d(c(x)) =
Answers: 2
question
Mathematics, 21.06.2019 18:10
Jordan has $5.37, which he is using to buy ingredients to make salsa. he is buying one red pepper for $1.29 and three pounds of tomatoes. if jordan has exactly the right amount of money he needs, what is the price per pound of the tomatoes? choose the correct equation to represent this real-world problem. solve the equation and verify the reasonableness of your answer. a pound of tomatoes costs .
Answers: 1
question
Mathematics, 21.06.2019 20:30
Secant be and cf intersect at point d inside a what is the measure of cde
Answers: 1
question
Mathematics, 21.06.2019 21:30
Using pert, adam munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 4. a) what is the probability that the project will be completed in 17 months? b) what is the probability that the project will be completed in 20 months? c) what is the probability that the project will be completed in 23 months? d) what is the probability that the project will be completed in 25 months? e) what is the due date that yields a 95% chance of completion?
Answers: 3
You know the right answer?
In a survey of 2,700 people who owned a certain type of car, 1,485 said they would buy that type of...
Questions
question
Mathematics, 15.07.2019 09:10
question
English, 15.07.2019 09:10
question
Mathematics, 15.07.2019 09:10
question
English, 15.07.2019 09:10
Questions on the website: 13722367