The critical path for a project was found to be 37 days. The variances total 27. What is probability of completing in 43 days? Below is information that might be useful to answer the question. Answer to 2 decimal points

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 20:50
Which of the following pair(s) of circles have las a common external tangent? select all that apply. a and b a and c b and c
Answers: 3
question
Mathematics, 21.06.2019 22:10
Aculture started with 2,000 bacteria. after 8 hours, it grew to 2,400 bacteria. predict how many bacteria will be present after 19 hours . round your answer to the nearest whole number. p=ae^kt
Answers: 1
question
Mathematics, 21.06.2019 23:30
Mason and christian go to the movie theater and purchase refreshments for their friends. mason spends a total of $45.75 on 3 bags of popcorn and 6 drinks. christian spends a total of $71.50 on 6 bags of popcorn and 4 drinks. write a system of equations that can be used to find the price of one bag of popcorn and the price of one drink. using these equations, determine and state the price of a drink, to the nearest cent.
Answers: 2
question
Mathematics, 22.06.2019 00:30
What is the solution for 6 - 7/8? explain the steps.
Answers: 1
You know the right answer?
The critical path for a project was found to be 37 days. The variances total 27. What is probability...