Mathematics, 01.09.2020 14:01 powellmj9216

A 12 1/2 mile stretch of road needs repaving . A company bids on the repaving project saying they could replace 2 1/4 miles of road per week. How many weeks will the company take to completely replace the stretch of road?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 14:00
Alawn mower manufacturer incurs a total of 34,816 in overhead costs and 388 per lawn mower in production costs. how many lawn mowers were manufactured if the average cost of productions is 660
Answers: 3
question
Mathematics, 21.06.2019 15:30
The average hourly earnings for a construction worker is projected to be $24.50 in 2012. jason wants to join the construction work force after he graduates in 2012. his friend tells him that average hourly earnings for construction workers will rise by 2% from 2009 to 2012. based on the data below, assuming that the projected hourly earnings are correct, is jason’s friend’s statement accurate? construction industry - average hourly earnings, 2000-2009 a. his friend’s statement is accurate. the average hourly earnings will increase by 2%. b. his friend’s statement is not accurate. the percent increase will be more than 2% c. his friend’s statement is not accurate. the percent increase will be less than 2% d. his friend’s statement is not accurate. the average hourly earnings will decrease
Answers: 3
question
Mathematics, 21.06.2019 20:30
Find the zeros of each function. f(x) = 6x^2 - 7x - 20
Answers: 1
question
Mathematics, 21.06.2019 21:30
What is the volume of this container?
Answers: 2
You know the right answer?
A 12 1/2 mile stretch of road needs repaving . A company bids on the repaving project saying they co...