Your company needs 15000 units/year, and it cost you 10$ to curry one unit and 200$ to place one
order.
If the lead time is 2 days what is the inventory
average?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 13:00
If kn = 9 cm, mn = 21 cm, rs = 42 cm, and ps = 18 cm, what is the scale factor of figure klmn to figure pqrs?
Answers: 3
question
Mathematics, 21.06.2019 16:30
Which expression is equivalent to sq-80
Answers: 2
question
Mathematics, 21.06.2019 22:30
The pair of coordinates that do not represent the point( 5,150’) is a. (5,-210) b. (5,210) c. (-5,330) d. (-5,-30)
Answers: 1
question
Mathematics, 21.06.2019 23:40
What is the equation, in point-slope form, of the line that has a slope of 6 and passes through the point (–1, –8)? a. y+8 = 6 (x+1 )
Answers: 1
You know the right answer?
Your company needs 15000 units/year, and it cost you 10$ to curry one unit and 200$ to place one
Questions
question
Mathematics, 05.03.2021 20:50
question
Mathematics, 05.03.2021 20:50
question
Mathematics, 05.03.2021 20:50
question
Mathematics, 05.03.2021 20:50
question
Mathematics, 05.03.2021 20:50
question
Mathematics, 05.03.2021 20:50
Questions on the website: 13722363