(i) You are the cost Engineer for a construction company in charge of building a new bridge. The construction company will be penalized each day of delay in
construction for bridge. The penalty will be $4500 for the first day and will increase
by $12000 for each following day. Based on its budget, the company can afford to
pay a maximum of $ 155000 toward penalty. By modelling this as an arithmetic
progression, find the maximum number of days by which the completion of work can
be delayed.

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 18:30
Acone with volume 1350 m³ is dilated by a scale factor of 1/3. what is the volume of the resulting cone? enter your answer in the box. m³
Answers: 1
question
Mathematics, 21.06.2019 19:30
Acabinmaker buys 3.5 liters of oat varnish the varnish cost $4.95 per liter what is the total cost of 3.5 liters
Answers: 1
question
Mathematics, 21.06.2019 22:00
Uestion 1(multiple choice worth 5 points) (05.02)alex wants to paint one side of his skateboard ramp with glow-in-the-dark paint, but he needs to know how much area he is painting. calculate the area of the isosceles trapezoid. isosceles trapezoid with top base 12 feet, bottom base of 18 feet, and height of 6 feet. 72 ft2 84 ft2 90 ft2 108 ft2
Answers: 1
question
Mathematics, 22.06.2019 00:00
Cody ran nine miles on his first day of training. the next day he ran 1/8 that distance. how far did he run the second day?
Answers: 2
You know the right answer?
(i) You are the cost Engineer for a construction company in charge of building a new bridge. The co...
Questions
question
Computers and Technology, 30.06.2019 20:00
Questions on the website: 13722366