Activity D on a CPM network has predecessors B and C: and has successor F. D has duration 6. B's earliest finish is 18: while C's is 20. F's late start is 26. Which of the following is definitely true? a. D is critical and has zero slack.
b. B is a critical activity.
c. F is critical and has zero slack.
d. D has no slack but is not critical.
e. C is completed before B.

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 19:00
What is the correlation coefficient between the variables? round to three decimal places. enter your answer in the box
Answers: 2
question
Mathematics, 21.06.2019 21:50
What is the 17th term in the arithmetic sequence in which a6 is 101 and a9 is 83
Answers: 1
question
Mathematics, 21.06.2019 22:30
Maria found the least common multiple of 6 and 15. her work is shown below. multiples of 6: 6, 12, 18, 24, 30, 36, 42, 48, 54, 60, . . multiples of 15: 15, 30, 45, 60, . . the least common multiple is 60. what is maria's error?
Answers: 1
question
Mathematics, 21.06.2019 23:00
Acarton of juice contains 64 ounces miss wilson bought six cartons of juice how many ounces of juice did she buy
Answers: 2
You know the right answer?
Activity D on a CPM network has predecessors B and C: and has successor F. D has duration 6. B's ear...
Questions
question
Mathematics, 19.09.2019 02:40
Questions on the website: 13722363