It took 20000 people 20 years to build taj Mahal each worker works at the same rate how long would it have taken for 8000 workers to build the taj Mahal

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 18:00
14. (05.02 lc) what is the value of y in the solution to the following system of equations? (5 points) 2x + y = −4 5x + 3y = −6
Answers: 1
question
Mathematics, 21.06.2019 22:30
Bob the builder is making 480kg of cement mix. this is made by cement, sand and gravel in the ratio 1: 3: 4
Answers: 3
question
Mathematics, 21.06.2019 23:00
In triangle △abc, ∠abc=90°, bh is an altitude. find the missing lengths. ac=26 and ch=8, find bh.
Answers: 3
question
Mathematics, 22.06.2019 00:00
Find the distance between the point (-3,-4), and (see the picture below)
Answers: 1
You know the right answer?
It took 20000 people 20 years to build taj Mahal each worker works at the same rate how long would i...
Questions
question
History, 20.04.2021 15:50
question
Biology, 20.04.2021 15:50
question
History, 20.04.2021 15:50
question
Biology, 20.04.2021 15:50
question
History, 20.04.2021 15:50
Questions on the website: 13722363