Mathematics, 11.10.2019 10:50 cathydaves

[50 points]

8 construction workers can build a house in 60 days. after working for 12 days, 4 more workers join in to build the house. how many days will they take to build the rest of the house?

show all workings and explain. : )


[50 points] 8 construction workers can build a house in 60 days. after working for 12 da

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 15:00
Find parametric equations for the line tangent to the curve of intersection of the surfaces at the given point. surfaces: xsquared2plus+2yplus+2zequals=1212 yequals=33 point: left parenthesis 1 comma 3 comma five halves right parenthesis
Answers: 1
question
Mathematics, 21.06.2019 15:20
Compare the subtraction problems 6/8 - 5/8 = 1/8 and 6/9 - 7/9 = 1/9 why is the answer to the first problem positive and the answer to the second problem negative
Answers: 1
question
Mathematics, 21.06.2019 21:30
In triangle △abc, ∠abc=90°, bh is an altitude. find the missing lengths. ah=4 and hc=1, find bh.
Answers: 2
question
Mathematics, 21.06.2019 22:10
On a piece of paper, graph y< x-1. then determine which answer choicematches the graph you drew.13. z3. 2(3.290-1)
Answers: 2
You know the right answer?
[50 points]

8 construction workers can build a house in 60 days. after working for 12 da...
Questions
question
Mathematics, 13.10.2020 05:01
question
Mathematics, 13.10.2020 05:01
question
Mathematics, 13.10.2020 05:01
Questions on the website: 13722363