Suppose task B follows task A. The likelihood that a problem will occur with task A is 0.5, and the time to correct the problem would be 2 months. The likelihood that a problem will occur with task B is 0.2, and the time to correct the problem would be 3 months. The risk consequence of both activities is 3.5 months 5.7 months 1.6 months cannot be determined. True or false?
Answers: 2
Mathematics, 21.06.2019 18:50
The trigonometric ratios sine and secant are reciprocals of each other
Answers: 2
Mathematics, 21.06.2019 19:30
Solve the following inequalities and show the solution on a number line. 3/4 (2x-7) ≤ 5
Answers: 1
Mathematics, 21.06.2019 21:30
Create a graph for the demand for starfish using the following data table: quantity/price of starfish quantity (x axis) of starfish in dozens price (y axis) of starfish per dozen 0 8 2 6 3 5 5 2 7 1 9 0 is the relationship between the price of starfish and the quantity demanded inverse or direct? why? how many dozens of starfish are demanded at a price of five? calculate the slope of the line between the prices of 6 (quantity of 2) and 1 (quantity of 7) per dozen. describe the line when there is a direct relationship between price and quantity.
Answers: 3
Mathematics, 22.06.2019 00:50
Randy and trey take turns cleaning offices on the weekends. it takes randy at most 4 hours to clean the offices. it takes trey at most 6 hours to clean the offices. what is the greatest amount of time it would take them to clean the offices together? 2.4 hours 2.5 hours
Answers: 3
Suppose task B follows task A. The likelihood that a problem will occur with task A is 0.5, and the...
Engineering, 12.01.2021 20:10
English, 12.01.2021 20:10
Mathematics, 12.01.2021 20:10
Mathematics, 12.01.2021 20:10
Mathematics, 12.01.2021 20:10
Mathematics, 12.01.2021 20:10
Mathematics, 12.01.2021 20:10