A project manager has determined that 3/10 of the work for a project was completed in 9 days. How many more days
will it take to finish the project if the work continues to progress at the same rate?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 12:30
If an x intercept only touches the x axis it means it has a multiplicity of 2. if an intercept goes through the axis it has a multiplicity of 1 true false
Answers: 1
question
Mathematics, 21.06.2019 14:30
If the measure of xyz is 81 what is the measure of yz
Answers: 3
question
Mathematics, 21.06.2019 17:30
Let f(x) = x+3 and g(x) = 1/x the graph of (fog)(x) is shown below what is the range of (fog)(x)?
Answers: 2
question
Mathematics, 21.06.2019 19:10
Alogical argument that is presented in graphical form using boxes and arrows is called?
Answers: 1
You know the right answer?
A project manager has determined that 3/10 of the work for a project was completed in 9 days. How ma...
Questions
Questions on the website: 13722363