A tire company has plants in Chicago and Detroit. The Chicago plant can make 600 radial and 100 standard tires per day. The Detroit plant can make 300 radial and 100 standard tires per day. It costs $4,000 per day to operate the Chicago plant and $3,000 per day to operate the Detroit plant. The company has a contract to make at least 24,000 radial and 5000 standard tires.
How many days should each plant be scheduled to minimize operating costs?
Answers: 1
Mathematics, 21.06.2019 19:30
When x = 3 and y = 5, by how much does the value of 3x2 – 2y exceed the value of 2x2 – 3y ?
Answers: 2
Mathematics, 21.06.2019 20:30
Venita is sewing new curtains. the table below shows the relationship between the number of stitches in a row and the length ofthe row.sewingnumber of stitches length (cm)51 131532024306what is the relationship between the number of stitches and the length? othe number of stitches istimes the length.o. the number of stitches is 3 times the length.
Answers: 2
A tire company has plants in Chicago and Detroit. The Chicago plant can make 600 radial and 100 stan...
Mathematics, 26.03.2021 16:40
Mathematics, 26.03.2021 16:40
Business, 26.03.2021 16:40
Mathematics, 26.03.2021 16:40
Mathematics, 26.03.2021 16:40
History, 26.03.2021 16:40
Mathematics, 26.03.2021 16:40
Biology, 26.03.2021 16:40
Mathematics, 26.03.2021 16:40
Geography, 26.03.2021 16:40