subject
Mathematics, 25.03.2020 18:25 avelyp

P = Predecessor S = Successor

This dependency states that you can start the successor after you start the predecessor. There is overlap between the two activities because you don't require 100% of the predecessor to be complete before starting the successor. Creating overlap will shorten the schedule, but it also increases risk. If something happens in the predecessor that impacts what you've already built in the successor, you'll end up redoing the successor work. The assumption with the SS dependency is moving both activities to start as soon as possible.

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 15:30
The coordinates of a, b, and c in the diagram are a(p,4), b(6,1), and c(9,q). which equation correctly relates p and q? hint: since is perpendicular to , the slope of Γ— the slope of = -1. a. p - q = 7 b. q - p = 7 c. -q - p = 7 d. p + q = 7
Answers: 3
question
Mathematics, 21.06.2019 20:00
Combine like terms to make a simpler expression 3z+z
Answers: 2
question
Mathematics, 22.06.2019 00:30
Which is an x-intercept of the graphed function? (0, 4) (–1, 0) (4, 0) (0, –1)
Answers: 2
question
Mathematics, 22.06.2019 03:00
Which statement is true about the local minimum of the graphed function? over the interval[-4,-2], the local minimum is 0. over the interval [-2,-1] , the local minimum is 25. over the interval [-1,4], the local minimum is 0. over the interval [4,7], the local minimum is -7
Answers: 2
You know the right answer?
P = Predecessor S = Successor

This dependency states that you can start the successor af...
Questions
question
Mathematics, 16.12.2021 21:20
question
Mathematics, 16.12.2021 21:30
question
Mathematics, 16.12.2021 21:30
question
Chemistry, 16.12.2021 21:30
question
Mathematics, 16.12.2021 21:30
Questions on the website: 13722363