An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day.

a) What are the minimum and maximum cycle times?
b) What range of output is theoretically possible for the line?
c) What is the minimum number of worksheets needed if the maximum output rate is to be sought?
d) What cycle time will provide an output rate of 125 units per day?
e) What output potential will result if the cycle time is (1) 9 minutes? and (2) 15 minutes?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 15:20
If x=-3 is the only x-intercept of the graph of a quadratic equation, which statement best discribes the discriminant of the equation?
Answers: 1
question
Mathematics, 21.06.2019 22:30
Ibeg you to me 20. a reaction produces 4.93 l of oxygen, but was supposed to produce 1 mol of oxygen. what is the percent yield?
Answers: 3
question
Mathematics, 21.06.2019 23:10
Statements reasons 1. ab ? cd; ad ? bc 1. given 2. ac ? ac 2. reflexive property 3. ? adc ? ? cba 3. ? 4. ? dac ? ? bca; ? acd ? ? cab 4. cpctc 5. ? dac and ? bca are alt. int. ? s; ? acd and ? cab are alt. int. ? s 5. definition of alternate interior angles 6. ab ? cd; ad ? bc 6. converse of the alternate interior angles theorem 7. abcd is a parallelogram 7. definition of parallelogram what is the missing reason in step 3?
Answers: 2
question
Mathematics, 22.06.2019 02:20
Of the 27 players trying out for the school basketball team, 8 are more than 6 feet tall and 7 have good aim. what is the probability that the coach would randomly pick a player over 6 feet tall or a player with a good aim? assume that no players over 6 feet tall have good aim. a. b. c. d.
Answers: 1
You know the right answer?
An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total tim...
Questions
Questions on the website: 13722363