Four jobs have uniformly distributed processing times, independently distributed on [10,15],[15,20],[10,20], and [15,25] respectively. There are three identical processors. Whenever a processor completes a job, it gets the next job on the schedule.

(a) Calculate the expected makespan for the schedule 1,2,3,4.(b) Calculate the expected flowtime for the schedule 1,2,3,4.(c) Calculate the expected makespan for the schedule 4,1,2,3.(d) Calculate the expected flowtime for the schedule 4,1,2,3.(e) Which schedule is better for flowtime? for makespan?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
27 is what percent of 108? 27 is % of 108
Answers: 2
question
Mathematics, 21.06.2019 19:00
If (x-2) 2= 49, then x could be a. -9 b. -7 c.- 2 d. 5 e.9
Answers: 2
question
Mathematics, 21.06.2019 21:00
Isabel graphed the following system of equations. 2x – y = 6 y = -3x + 4 she came up with the solution (2,-2). what were the 3 steps she did to get that solution? (make sure they are in the correct order)
Answers: 2
question
Mathematics, 21.06.2019 21:50
(x-5)1/2+5=2 what is possible solution of this equation
Answers: 1
You know the right answer?
Four jobs have uniformly distributed processing times, independently distributed on [10,15],[15,20],...
Questions
question
Mathematics, 09.11.2020 21:50
question
Mathematics, 09.11.2020 21:50
question
Mathematics, 09.11.2020 21:50
question
Mathematics, 09.11.2020 21:50
Questions on the website: 13722367