Suppose a particular project has an expected completion time of 30 days; in other words, the critical path takes 30 days to finish. Further, the variance of the critical path is 25. Based on this information, please answer the following questions:

Find the probability that the project:
(1) Would be completed within 40 days
(2) Would take longer than 40 days to finish
(3) Would be completed within 20 days
(4) Would take longer than 20 days to finish

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 17:30
Afarmer sells 9.5 kilograms of apples and pears at the farmer's market. 4/5 of the weight is the apples and the rest is the pears. how many kilograms of pears did she sell at the farmers market
Answers: 1
question
Mathematics, 21.06.2019 18:00
Solutions for 2x+7 less than or equal to 3x-5
Answers: 1
question
Mathematics, 21.06.2019 19:30
What are the exclude value of mn+3m
Answers: 1
question
Mathematics, 21.06.2019 22:30
There were 25 students who answered to a survey about sports. four-fifths of them like football. how many students like football?
Answers: 2
You know the right answer?
Suppose a particular project has an expected completion time of 30 days; in other words, the critica...
Questions
question
Mathematics, 10.02.2021 01:30
question
Biology, 10.02.2021 01:30
question
Mathematics, 10.02.2021 01:30
question
Mathematics, 10.02.2021 01:30
question
Chemistry, 10.02.2021 01:30
question
Mathematics, 10.02.2021 01:30
Questions on the website: 13722366