22. the time t required to do a job varies inversely as the number of people p working. it takes 3
hours for 7 volunteers to pick up rubbish from 1 mile of roadway. how long would it take 12
volunteers to complete the job?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 18:30
Write the rational number in lowest terms 99/-15
Answers: 2
question
Mathematics, 21.06.2019 19:40
Afactory makes propeller drive shafts for ships. a quality assurance engineer at the factory needs to estimate the true mean length of the shafts. she randomly selects four drive shafts made at the factory, measures their lengths, and finds their sample mean to be 1000 mm. the lengths are known to follow a normal distribution whose standard deviation is 2 mm. calculate a 95% confidence interval for the true mean length of the shafts. input your answers for the margin of error, lower bound, and upper bound.
Answers: 3
question
Mathematics, 21.06.2019 22:00
To decrease an amount by 16% what single multiplier would you use
Answers: 1
question
Mathematics, 22.06.2019 00:00
Which choice names the hypotenuse of triangle xyz? a. segment yx b. segment yz c. segment ab d. segment zx
Answers: 3
You know the right answer?
22. the time t required to do a job varies inversely as the number of people p working. it takes 3
Questions
question
Mathematics, 24.03.2021 14:00
question
Mathematics, 24.03.2021 14:00
question
Geography, 24.03.2021 14:00
question
Chemistry, 24.03.2021 14:00
Questions on the website: 13722367