Mathematics, 05.12.2019 11:31 astridantonio225

8men will take 10 days to build a wall 150 metres long. after the men had started working for 6 days, they were told that the wall needed to by lengthened by 45 metres. how many more men must be hired to complete the job on time?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 14:40
What signals you that factoring by grouping is the best method to use when factoring a problem?
Answers: 2
question
Mathematics, 21.06.2019 18:30
Tyler enjoys the fish so much that after his birthday his family decides to take him to a famous aquarium a tank at the aquarium is similar to his tank with the scale factor of 8 how many times greater is the volume of the tank at the aquarium than the volume of tyler tank
Answers: 2
question
Mathematics, 21.06.2019 23:00
The ratio of the perimeters of two similar triangles is 4: 3. what are the areas of these triangles if the sum of their areas is 130cm2?
Answers: 3
question
Mathematics, 21.06.2019 23:50
Which function has the domain x> -11? y= x+ 11 +5 y= x-11 +5 y= x+5 - 11 y= x+5 + 11
Answers: 2
You know the right answer?
8men will take 10 days to build a wall 150 metres long. after the men had started working for 6 days...
Questions
question
Mathematics, 28.06.2019 15:00
question
Mathematics, 28.06.2019 15:00
question
Mathematics, 28.06.2019 15:00
question
Computers and Technology, 28.06.2019 15:00
Questions on the website: 13722367